Subcontractor Performance & Trade Coordination Intelligence

Horizon Pacific General Contractors — Portfolio Analytics (Q4 2024)

Data as of
Dec 15, 2024
Portfolio Avg PPC Score
58%
↓ 3.2% vs Q3
Avg Punch List Density
2.8
items/$100K
Portfolio TRIR
2.4
↑ 0.6 vs target
Avg Bid-to-Final Var
+6.2%
↑ $1.8M leakage
Avg Submittal Days
14.2
Target: 10d
Payment Accuracy
91%
↑ 2% vs Q3

Subcontractor Composite Performance Scorecard (Top 14 by Volume)

Rank Subcontractor Trade Composite Score PPC % Punch/$100K TRIR Bid-to-Final Projects (3yr) Avg Award
1 Precision Electrical Electrical 87 76% 1.2 0.8 +1.2% 9 $1.8M
2 SteelFrame Pro Structural Steel 82 72% 0.9 1.1 -0.5% 7 $3.2M
3 Cascade Plumbing Plumbing 79 68% 1.8 1.4 +2.1% 11 $1.4M
4 Pacific Fire Protection Fire Protection 76 71% 2.1 1.6 +3.4% 8 $980K
5 Modern Drywall Systems Drywall 68 62% 3.2 2.1 +4.8% 12 $840K
6 Elite Glazing Co Glass/Glazing 65 59% 2.8 1.9 +5.3% 6 $1.1M
7 Summit Concrete Concrete 61 56% 2.4 2.8 +6.1% 10 $2.1M
8 Northwest Roofing Roofing 58 53% 3.6 2.6 +7.2% 5 $920K
9 Skyline Masonry Masonry 54 51% 3.1 3.2 +8.4% 4 $760K
10 Coastal Flooring Flooring 52 49% 4.1 2.4 +9.1% 8 $640K
11 Metro Painting Painting 47 46% 5.2 3.4 +10.8% 9 $520K
12 Titan Earthworks Sitework 43 47% 3.8 4.1 +9.6% 5 $1.3M
13 Alliance HVAC HVAC 41 48% 3.6 3.6 +8.9% 3 $2.6M
14 Apex Thermal Systems HVAC 38 44% 4.2 3.8 +11.2% 6 $2.4M

Bid-to-Final-Cost Variance by Subcontractor (Last 12 Months)

Back-Charge Frequency (Q4 2024)

Punch List Density by Trade

Safety (TRIR) by Trade

Man-Day Productivity Index

Coordination Clash Rate by Trade Pair (Clashes per 10K SF)

HVAC
Plumbing
Electrical
Fire Prot
Struct
Arch
MEP Gen
HVAC
8.2
5.4
3.1
1.8
0.9
2.6
Plumbing
8.2
4.7
2.9
1.2
0.6
2.1
Electrical
5.4
4.7
3.4
1.6
0.8
2.3
Fire Prot
3.1
2.9
3.4
1.1
0.4
1.9
Structural
1.8
1.2
1.6
1.1
0.3
1.4
Architectural
0.9
0.6
0.8
0.4
0.3
0.5
MEP General
2.6
2.1
2.3
1.9
1.4
0.5

HVAC-Plumbing coordination drives highest clash density; structural and architectural interfaces show minimal conflicts

Back-Charge History by Subcontractor (Last 6 Months)

Change Order Initiation Rate by Subcontractor

Submittal Response Time Distribution (Days)

Payment Application Accuracy

SubcontractorAccuracy %
Precision Electrical98%
SteelFrame Pro96%
Cascade Plumbing94%
Pacific Fire Protection93%
Modern Drywall88%
Elite Glazing86%
Summit Concrete84%
Apex Thermal76%

Apex Thermal Systems — Performance Risk Profile

Project History (3 Years)

Westlake Medical Center
$2.8M | +14.2% variance | TRIR 4.2
Parkside High School
$2.1M | +9.8% variance | TRIR 3.6
Urban Plaza Mixed-Use
$2.6M | +10.4% variance | TRIR 3.4
Riverbend Office Tower
$2.3M | +12.1% variance | TRIR 4.1
RECOMMENDATION
Do not award next competitive bid without performance improvement plan and surety bonding.