Schedule Performance & Delay Risk Analytics

Cascade Pacific Construction | Riverside Medical Office Building | Week 16 of 28

Contract Value
$22.4M
Schedule Complete
52%
Portfolio SPI
0.87
↓ -0.07 vs. Week 12
Critical Float (days)
3.2
↓ -4.8 days in 4 wks
Avg PPC (6 wks)
67%
↓ -8% vs. baseline
Constraints >14d
14
↑ +6 from last month
Lookahead Accuracy
71%
↓ -5% this period
Milestone Slip Index
1.18
↑ +0.18 vs. target

Critical Path Float Erosion — Last 12 Weeks

Percent Plan Complete (PPC) by Subcontractor × Week

Wk 11
Wk 12
Wk 13
Wk 14
Wk 15
Wk 16
Cascade Mechanical
48%
42%
44%
41%
46%
44%
Summit Electric
72%
68%
74%
71%
69%
73%
Precision Drywall
88%
91%
86%
89%
92%
90%
BlueSky Plumbing
78%
82%
76%
79%
81%
77%
Apex Structural
94%
96%
93%
95%
97%
94%
>80%
60-80%
<60%

Constraint Log Age Distribution

Schedule Risk Register — Top 10 Activity Chains at Risk

Activity Chain Current Float Erosion Rate Slip Prob (6wk) Impact (days) Status Owner
MEP Rough-In → Ceiling Grid Install 1.2d -1.4 d/wk 68% +18d Critical J. Morrison
Exterior Glazing → Interior Finish 3.8d -0.9 d/wk 52% +14d Critical A. Chen
Fire Sprinkler Test → Ceiling Close 5.1d -0.7 d/wk 44% +12d Watch T. Rodriguez
Elevator Install → Floor 3 Access 6.4d -0.5 d/wk 38% +16d Watch K. Patel
Roof Membrane → Rooftop Unit Set 2.9d -1.1 d/wk 56% +9d Critical M. Davis
Underground Utilities → Paving 8.2d -0.3 d/wk 22% +7d Monitor S. Wright
Floor 2 Drywall → Paint Prime 4.7d -0.6 d/wk 41% +11d Watch L. Kim
Main Electrical Room → Panel Install 7.1d -0.4 d/wk 28% +10d Monitor R. Singh

Lookahead Commitment Accuracy

Weather Delay Buffer

68%
Consumed (13.6 of 20 days)
6.4 days remaining buffer

Pull Planning Session Rate

83%
5 of 6 sessions completed
Week 13
Week 14
Week 15
Week 16

Resource Loading Variance by Trade (Planned vs. Actual)

RFI Cycle Time by Design Discipline

Project Milestone Status — Key Deliverable Dates