Cost Control & Budget Variance Intelligence
| CO # | Description | Type | Cost Impact | Client Approved | Recovery % | Status |
|---|---|---|---|---|---|---|
| CO-041 | Structural Steel Rerate — Design Change | Design | $4,200,000 | $3,100,000 | 73.8% | Approved |
| CO-044 | Differing Ground Conditions — Piling | Site | $2,600,000 | $0 | 0.0% | Disputed |
| CO-051 | Prelim Extension — 4 months | Time | $1,200,000 | $0 | 0.0% | Under Review |
| CO-038 | MEP Coordination — Clash Resolution | Design | $980,000 | $820,000 | 83.7% | Approved |
| CO-052 | Fire Protection Upgrade — Code Change | Regulatory | $760,000 | $680,000 | 89.5% | Approved |
| CO-029 | Formwork Acceleration — Schedule Recovery | Time | $540,000 | $320,000 | 59.3% | Approved |
| CO-047 | Glazing System Substitution | Design | $420,000 | $420,000 | 100.0% | Approved |
| CO-053 | Asbestos Remediation — Unforeseen | Site | $380,000 | $0 | 0.0% | Pending |
| CO-034 | Landscaping Scope Addition | Scope | $310,000 | $310,000 | 100.0% | Approved |
| CO-049 | Temporary Works — Tower Crane Extension | Site | $280,000 | $160,000 | 57.1% | Approved |