Schedule Performance & Milestone Adherence

Meridian Infrastructure — Terminal Expansion ($280M, Month 28/42)

P6 Last Update
2025-01-15 18:22 UTC
Schedule Performance Index
0.87
-0.08 vs target
Critical Path Float
4d
-18d vs M20
Milestone Slip
18d
Structural Topping Out
Float Burn Rate
2.25d/wk
8-week avg
Milestone Compliance
72%
13/18 met on forecast
Earned Schedule Variance
-21d
Behind baseline schedule
Worst Package SPI
0.74
Steel Erection
Excusable Delay Bank
7d
of 18 remaining
Acceleration Cost Index
1.14
$2.8M recovery spend
Planned vs Actual Δ%
-6.2%
Cumulative variance

Planned vs Actual Progress S-Curve (Cumulative %)

Milestone Slip vs Baseline (days)

Float Consumption Trend (days remaining)

Work Package Risk Analysis

Work Package SPI Float (d) Δ% Complete Productivity Predecessor Lag Status
Steel Erection0.740-8.4%0.68+12dCRITICAL
Concrete Foundations0.922-2.1%0.89+3dWATCH
Electrical Rough-In0.811-5.6%0.76+7dCRITICAL
HVAC Installation0.884-3.8%0.84+5dWATCH
Facade Cladding0.968-1.2%0.94+1dON TRACK
Fire Protection0.946-1.8%0.91+2dON TRACK
Plumbing0.863-4.2%0.82+6dWATCH
Interior Framing0.9812+0.5%0.990dON TRACK
Roofing0.791-7.1%0.73+9dCRITICAL
Site Utilities1.0214+1.2%1.04-2dON TRACK
Concrete Slabs0.915-2.6%0.88+4dWATCH
Architectural Finishes0.877-4.0%0.85+5dWATCH

Subcontractor Productivity Factor by Trade

SPI Trend by Key Work Package (8-week)

Excusable Delay Bank

Weather Days Used11
Permitting Delays0
Owner Changes0
Total Consumed11 / 18
Remaining7 days

Acceleration Cost Index

Overtime Premium$1.2M
Crew Augmentation$0.9M
Equipment Rental$0.5M
Expedited Materials$0.2M
Total Recovery Spend$2.8M
ACI1.14

Critical Float Breach Risk

Packages at 0d Float3
Packages <5d Float7
LD Trigger Probability68%
Days to LD Event~22d
Based on current float burn rate (2.25 d/wk) and critical path exposure
Data Source: Oracle Primavera P6 EPPM | Procore Daily Logs | Weather API | Last reconciled: 2025-01-15 18:22 UTC
Baseline: April 2023 IFC Schedule Rev 4