PM Compliance & Failure Avoidance Dashboard

Meridian Industrial — 13 Weeks Ending Week 13 (Current Period)

Goal: <12% Emergency WO Ratio
Target Savings: $180K/Quarter
PM Adherence Rate
81.4%
-9.8% from W1
Emergency WO Ratio
19.2%
+5.8pp vs target
MTBF (Days)
47.2
-12.4 vs 90d avg
Deferred Backlog
$89.2K
+$14.3K MoM
Wrench Time %
62.1%
+3.2pp QoQ
MTTR (Hours)
6.8
+1.4hr vs baseline

PM Adherence vs. Emergency WO Ratio — 13-Week Trend

MTBF by Asset Class — 90-Day Rolling

Planned vs. Reactive Cost Ratio

Technician PM Completion Rate — Rolling 4 Weeks

Week 10
Week 11
Week 12
Week 13
Martinez, R.
94%
96%
92%
93%
Chen, L.
87%
89%
86%
88%
Thompson, M.
71%
68%
74%
76%
Garcia, J.
84%
82%
85%
90%
Williams, K.
91%
93%
88%
91%
Patel, A.
79%
81%
77%
83%
≥90% (Target)
80-89%
<80% (At Risk)

Parts Fill Rate by Asset Class

Asset Criticality-Weighted Compliance

Critical Assets (Tier 1) 76.2%
High Priority (Tier 2) 82.4%
Standard (Tier 3) 88.1%
Low Priority (Tier 4) 91.3%
Alert
Critical asset compliance 23.8pp below target — 18 Tier 1 assets have missed ≥2 consecutive PM cycles

Asset-Level PM Work Order Detail — Overdue & At-Risk

Asset ID Class Criticality PM Due Date Days Overdue Assigned Tech Status
CONV-07 Conveyor Belt Tier 1 Mar 18 12 Thompson, M. Overdue
PUMP-14 Hydraulic Pump Tier 1 Mar 22 8 Patel, A. Overdue
COMP-03 Air Compressor Tier 2 Mar 25 5 Chen, L. Overdue
CONV-11 Conveyor Belt Tier 1 Mar 26 4 Thompson, M. Overdue
TANK-08 Storage Tank Tier 2 Apr 2 -2 Williams, K. Due Soon
HEAT-05 Heat Exchanger Tier 1 Apr 5 -5 Martinez, R. Due Soon
VALVE-19 Control Valve Tier 3 Apr 8 -8 Garcia, J. Due Soon
MOT-12 Electric Motor Tier 2 Apr 10 -10 Patel, A. Due Soon