Spare Parts & MRO Inventory Readiness

Titan Steel Rolling · 3 Mills · 1,800 Active MRO SKUs

Parts Availability
88%
-3% vs target
Critical Spare Coverage
91%
-4% vs 95% goal
Stockout Rate
7%
↑ vs 5% target
Emergency POs/mo
28
-12% MoM
Mean Parts Delay
5.2h
per delayed WO
Downtime Cost
$94K
parts shortage MTD

SKU Readiness by Site (Critical A-Class Parts)

Mill 1
Mill 2
Mill 3
Hydraulic Pumps
98%
74%
92%
Bearing Sets
91%
85%
96%
Motor Starters
100%
100%
94%
Seal Kits
93%
79%
88%
Sensors/Switches
86%
90%
92%
Belts & Couplings
97%
91%
95%

Mill 2 hydraulic pump seal kit stockout drove 52h cumulative delay

Stockout Rate by ABC Classification

Emergency Purchase Orders (12 weeks)

Top 10 SKUs Causing Work Order Delays

SKU Description Class Site Stockouts (90d) Cumulative Delay (h) Cost Impact
HYD-2847 Hydraulic Pump Seal Kit A Mill 2 4 52 $28,600
BRG-1923 Rolling Mill Bearing Set A Mill 1 3 38 $19,400
MTR-5501 AC Motor Starter 480V B Mill 3 5 29 $14,200
SNS-3342 Proximity Sensor 24VDC B Mill 2 6 24 $11,800
HYD-4712 Hydraulic Hose Assembly A Mill 1 2 22 $10,500
BLT-8834 V-Belt Drive Set C Mill 3 7 18 $6,300
FLT-2291 Oil Filter Element B Mill 2 4 16 $5,900
VLV-6623 Pneumatic Control Valve A Mill 1 2 14 $5,400
CPL-9012 Shaft Coupling Assembly B Mill 3 3 12 $4,200
SWT-7745 Limit Switch DPDT C Mill 2 5 10 $3,100

Forecast Accuracy vs Stockout Rate

Each point = one SKU category; size = total usage volume

Inventory Carrying Cost Distribution

Obsolete stock post-retrofit: $340K

Supplier Lead-Time Adherence (12 weeks)

Week 6 bearing supplier delay: +8 days vs committed lead time