Shop Floor OEE & Throughput — Real-Time

MidWest Precision Components LLC • Day Shift • 6.5h Elapsed (06:00–14:00)

Last Updated
12:32:17
Plant OEE
74.3%
-3.2%
Availability
81.2%
-4.8%
Performance
91.5%
+1.1%
First-Pass Yield
95.8%
-0.9%
Schedule Attain.
85.6%
-2.4%
Units/Hour
847
vs 930 takt

OEE Loss Waterfall — Day Shift

Line OEE Comparison

MTBF/MTTR by Line (Hours)

Changeover SMED Delta

Scrap Cost per 1K Units

Speed Loss Index

Machine State Grid — Real-Time

Line 1
86.7%
Running
Line 2
79.4%
Running
Line 3
61.2%
Repair (52m)
Line 4
73.1%
Changeover
Line 5
81.9%
Running
Line 6
77.8%
Running

First-Pass Yield by Work Center

Downtime Pareto (Minutes)

Production Order Detail — Active & Recent

Order ID Line Part # Target Actual Scrap OEE Status
WO-34128 Line 1 MP-4762A 2,400 2,341 18 86.7% Running
WO-34129 Line 2 MP-5214B 1,800 1,567 22 79.4% Running
WO-34130 Line 3 MP-6891C 2,100 1,214 47 61.2% Repair
WO-34131 Line 4 MP-3347A 1,600 1,189 12 73.1% Changeover
WO-34132 Line 5 MP-7823D 2,200 1,923 31 81.9% Running
WO-34133 Line 6 MP-1092E 1,900 1,534 28 77.8% Running
WO-34127 Line 1 MP-2451F 2,000 2,000 9 91.2% Complete
WO-34126 Line 3 MP-6891C 1,500 1,477 14 88.4% Complete

Shift Comparison — Day / Afternoon / Night