Stratos Group Portfolio • Q3 2024 • Updated 2 hours ago
| ID | Type | Description | Severity | Propagation | Projects Impacted | Owner | Age (d) |
|---|---|---|---|---|---|---|---|
| R-041 | Risk | DataBridge API delay (6 weeks) | Critical | 4 | Orion, Nexus, Atlas, Titan | K. Martinez | 22 |
| R-038 | Risk | Senior engineer attrition (2 resignations) | High | 3 | Nexus, Atlas, Catalyst | D. Chen | 15 |
| I-112 | Issue | Orion-Nexus dependency breach (milestone slip) | High | 2 | Nexus, Titan | J. Park | 8 |
| R-044 | Risk | Budget overrun — Catalyst infra costs (+18%) | High | 1 | Catalyst | Unassigned | 34 |
| R-036 | Risk | Security compliance delay (SOC 2 audit) | Medium | 3 | Orion, Nexus, Prism | A. Robinson | 41 |
| I-108 | Issue | Atlas-Prism integration test failures (23 defects) | Medium | 2 | Atlas, Prism | M. Singh | 12 |
| R-042 | Risk | Titan UAT resource contention (Q3 schedule conflict) | High | 2 | Titan, Catalyst | L. Torres | 19 |
| R-040 | Risk | Vendor contract renewal uncertainty (CloudCore) | Medium | 1 | Orion | F. Watson | 27 |