Energy Transition & Renewable Mix Progress

Pacific Ceramics · RE100 Member · 31 Sites · Target: 72% renewable by 2027

Last Updated
Dec 2024
Renewable Share
58%
+4% YoY
Energy Intensity
0.82
kWh/unit
-8% vs baseline
Scope 2 Delta
14%
Location - Market
Grid factor update
Decarbonization Capex
87%
vs. Plan
Slippage in TX
On-Site Generation
12.4
GWh YTD
+18% YoY
Milestone Slippage
4
Projects Delayed
Critical attention

Renewable Mix by Region

Solar
Wind PPAs
RECs
Grid (Non-Renewable)

Energy Intensity vs. Target

Target: -12% by 2027 (0.79 kWh/unit)

PPA Forward Coverage

6.2 years
Average contract coverage across renewable PPAs
Target: ≥5 years forward

Scope 2 Emissions Bridge (Location → Market-Based)

Grid factor update added 3.2K tCO2e to location-based total

Decarbonization Project Timeline

Project Site Type Status Timeline Slippage
Texas Plant 7 Solar Tyler, TX On-site solar Delayed Q1 2024 → Q2 2024 +4 months
Ohio PPA Expansion Cleveland, OH Wind PPA On Track Q2 2024 —
California LED Retrofit San Jose, CA Efficiency Complete Q4 2023 —
Georgia HVAC Upgrade Atlanta, GA Efficiency Delayed Q3 2024 → Q4 2024 +2 months
Arizona Solar Carport Phoenix, AZ On-site solar On Track Q3 2024 —
NY Wind PPA Contract Buffalo, NY Wind PPA Delayed Q2 2024 → Q3 2024 +3 months
Michigan Battery Storage Detroit, MI Storage Planning Q1 2025 —
Pennsylvania REC Purchase Pittsburgh, PA REC procurement Delayed Q4 2024 +1 month

Top 15 Sites — Renewable Mix

Site Region Renewable % Consumption (MWh) Mix
San Jose Plant 1 Pacific 92% 8,420 Excellent
Phoenix Facility 3 Southwest 87% 6,210 Excellent
Denver Operations Mountain 78% 5,890 Good
Portland Manufacturing Pacific NW 74% 7,150 Good
Boston Distribution Northeast 68% 4,320 Fair
Cleveland Hub Midwest 61% 9,540 Fair
Atlanta Plant 5 Southeast 58% 6,780 Fair
Chicago Warehouse Midwest 56% 5,120 Fair
Tyler Plant 7 Texas 54% 11,230 Below Target
Dallas Facility Texas 52% 8,950 Fair
Houston Operations Texas 49% 7,640 Fair
Pittsburgh Plant 2 Northeast 47% 6,420 Below Target
Detroit Manufacturing Midwest 44% 9,870 Below Target
Buffalo Distribution Northeast 41% 4,560 Below Target
Memphis Warehouse Southeast 38% 5,230 Below Target
Texas Plant 7 renewable share dropped from 58% to 54% due to solar installation delay
Industry Benchmark
Competitor TerraTile reports 63% renewable electricity share vs. Pacific Ceramics 58%. Texas region slippage is primary gap driver.