Energy Transition & Renewable Mix Progress

Pacific Ceramics · RE100 Member · 31 Sites · Target: 72% renewable by 2027

Last Updated
Dec 2024
Renewable Share
58%
+4% YoY
Energy Intensity
0.82
kWh/unit
-8% vs baseline
Scope 2 Delta
14%
Location - Market
Grid factor update
Decarbonization Capex
87%
vs. Plan
Slippage in TX
On-Site Generation
12.4
GWh YTD
+18% YoY
Milestone Slippage
4
Projects Delayed
Critical attention

Renewable Mix by Region

Solar
Wind PPAs
RECs
Grid (Non-Renewable)

Energy Intensity vs. Target

Target: -12% by 2027 (0.79 kWh/unit)

PPA Forward Coverage

6.2 years
Average contract coverage across renewable PPAs
Target: ≥5 years forward

Scope 2 Emissions Bridge (Location → Market-Based)

Grid factor update added 3.2K tCO2e to location-based total

Decarbonization Project Timeline

Project Site Type Status Timeline Slippage
Texas Plant 7 Solar Tyler, TX On-site solar Delayed Q1 2024 → Q2 2024 +4 months
Ohio PPA Expansion Cleveland, OH Wind PPA On Track Q2 2024
California LED Retrofit San Jose, CA Efficiency Complete Q4 2023
Georgia HVAC Upgrade Atlanta, GA Efficiency Delayed Q3 2024 → Q4 2024 +2 months
Arizona Solar Carport Phoenix, AZ On-site solar On Track Q3 2024
NY Wind PPA Contract Buffalo, NY Wind PPA Delayed Q2 2024 → Q3 2024 +3 months
Michigan Battery Storage Detroit, MI Storage Planning Q1 2025
Pennsylvania REC Purchase Pittsburgh, PA REC procurement Delayed Q4 2024 +1 month

Top 15 Sites — Renewable Mix

Site Region Renewable % Consumption (MWh) Mix
San Jose Plant 1 Pacific 92% 8,420 Excellent
Phoenix Facility 3 Southwest 87% 6,210 Excellent
Denver Operations Mountain 78% 5,890 Good
Portland Manufacturing Pacific NW 74% 7,150 Good
Boston Distribution Northeast 68% 4,320 Fair
Cleveland Hub Midwest 61% 9,540 Fair
Atlanta Plant 5 Southeast 58% 6,780 Fair
Chicago Warehouse Midwest 56% 5,120 Fair
Tyler Plant 7 Texas 54% 11,230 Below Target
Dallas Facility Texas 52% 8,950 Fair
Houston Operations Texas 49% 7,640 Fair
Pittsburgh Plant 2 Northeast 47% 6,420 Below Target
Detroit Manufacturing Midwest 44% 9,870 Below Target
Buffalo Distribution Northeast 41% 4,560 Below Target
Memphis Warehouse Southeast 38% 5,230 Below Target
Texas Plant 7 renewable share dropped from 58% to 54% due to solar installation delay
Industry Benchmark
Competitor TerraTile reports 63% renewable electricity share vs. Pacific Ceramics 58%. Texas region slippage is primary gap driver.