Capital Budget & Project Portfolio Tracker

Ironbridge Infrastructure Partners — $24.3M Active Capital Program

Portfolio CPI
0.87
↓ 13% below target
Portfolio SPI
0.91
↓ 9% behind schedule
Capital Absorption
$1.82M
/week avg
Contingency Burn
43%
↓ 6% vs last period
Committed Capital
$19.7M
81% of approved
Stalled Projects
3
$4.1M locked capital

Portfolio Performance Matrix

Each bubble represents a project sized by approved budget. Critical zone: CPI or SPI below 0.85

Portfolio Earned Value S-Curve

Critical Alerts

ERP Cloud Migration
CPI 0.76 | 78% contingency burned at 52% complete
6-week delay, integrator failure
Data Center Consolidation
Stalled 67 days | $1.4M locked capital
Pending vendor selection
Fleet Management System
SPI 0.82 | Integration delays
Rebaseline required

Project Timeline & Status

Committed-to-Approved Ratio

Contingency Reserve Status

CPI Distribution

SPI Distribution

Milestone Performance

Project Detail View

Project Name Business Unit Total Budget Spent Committed CPI SPI % Complete Status
ERP Cloud Migration IT & Digital $3,200,000 $2,456,000 $2,890,000 0.76 0.88 52% Critical
Data Center Consolidation IT & Digital $2,800,000 $1,420,000 $1,820,000 0.89 0.62 38% Stalled
Fleet Management System Operations $1,950,000 $1,240,000 $1,680,000 0.91 0.82 61% At Risk
Building Automation Upgrade Facilities $1,680,000 $1,380,000 $1,540,000 1.04 1.02 84% On Track
HVAC System Replacement Facilities $1,420,000 $920,000 $1,180,000 0.98 0.96 68% On Track
Security Infrastructure Facilities $1,280,000 $840,000 $1,120,000 0.87 0.89 72% At Risk
Warehouse Expansion Operations $2,600,000 $1,680,000 $2,340,000 0.94 0.97 76% On Track
Asset Tracking Platform Operations $890,000 $620,000 $780,000 1.02 1.08 89% On Track

Unfunded Pipeline Value by Priority

Capital Reallocation Activity

From: Data Center Consolidation -$280K
To: ERP Cloud Migration +$280K
From: Security Infrastructure -$150K
To: Fleet Management System +$150K
Total Reallocated (Q4)
$1.24M