Capital Expenditure Portfolio Oversight

Hartwell Industrial Group · FY2024 · $142.8M Active Portfolio

Last Updated
Dec 15, 2024 14:30
Total Portfolio Budget
$142.8M
Approved Envelope
Actual Spend YTD
$87.4M
61.2% utilized
Forecast at Completion
$151.2M
+$8.4M variance
Portfolio CPI
0.94
Below target 1.00
Contingency Burn Rate
78%
vs 62% complete
At-Risk Projects
4 / 17
CPI < 0.90

Project Performance Matrix — CPI × SPI

On Track (CPI>0.95, SPI>0.95)
Watch (CPI 0.90–0.95)
At Risk (CPI<0.90)

Committed vs Approved Budget by Phase

Contingency Burn vs Schedule Progress

Change Order Volume & Approval Rate (Last 90 Days)

Forecast at Completion Trend — Top 5 Projects

Active Project Portfolio

Project Budget Actual FAC Variance CPI SPI % Complete Status
FORGE Facility $38.0M $27.8M $45.2M +$7.2M 0.84 0.91 73% At Risk
ERP Implementation $22.0M $18.4M $22.6M +$0.6M 0.94 0.98 84% Watch
Warehouse Expansion $14.5M $8.2M $14.1M -$0.4M 1.03 1.01 58% On Track
Equipment Modernization $12.8M $7.1M $13.2M +$0.4M 0.97 0.92 55% On Track
Quality Lab Build-out $9.2M $6.8M $10.4M +$1.2M 0.88 0.94 74% At Risk
IT Infrastructure Upgrade $8.4M $5.2M $8.6M +$0.2M 0.98 0.99 62% On Track
Sustainability Initiative $6.9M $3.1M $7.1M +$0.2M 0.94 0.96 45% Watch
Robotics Integration $5.8M $4.3M $6.6M +$0.8M 0.88 0.89 74% At Risk

Operations

$64.2M
of $68.0M budget
94% utilized

Technology

$27.8M
of $30.8M budget
90% utilized

Facilities

$38.4M
of $44.0M budget
87% utilized

Vendor Invoice vs Milestone Payment Adherence

Portfolio Reforecast Accuracy (Bias Score)

Q1 2024 -2.4%
Q2 2024 +3.8%
Q3 2024 +5.9%
Q4 2024 (Projected) +4.2%
Bias score indicates systematic over- or under-estimation. Positive bias = underestimating costs.
Data as of December 15, 2024 · Hartwell Industrial Group CFO Office · Confidential