Parts, Van Stock & Inventory Readiness

ThermoCare Commercial · 310 Vans · 2,400 Active SKUs

Week Ending
Nov 8, 2024
First Visit Avail.
86.2%
-2.1%
Van Stockout Rate
9.0%
+1.4%
Emergency Runs
41
/week
Pick Accuracy
97.2%
-0.8%
Mean Delay Hours
3.8h
per delayed job
2nd Trip (Parts)
11%
of all second trips

SKU Readiness by Region

North
South
East
West
Central
TXV Valve
72%
68%
81%
70%
78%
Contactor
74%
83%
76%
80%
91%
Capacitor
92%
89%
94%
87%
90%
Filter Drier
95%
93%
96%
91%
94%
Relay
84%
82%
88%
85%
89%
Thermostat
97%
96%
98%
95%
97%

Stockout Rate by SKU Category

Emergency Parts Runs (8 Weeks)

Top 16 SKUs Driving Job Delays

SKU Description Stockouts Delayed Jobs Avg Delay (h) MAPE (%)
TXV-450TXV Valve 3/8"38324.228.4
CTR-220Contactor 30A29263.922.1
CAP-370Capacitor 370V 45µF18152.814.2
FDR-083Filter Drier 3/8"12103.111.6
RLY-120Relay 24V SPST15133.518.7
THM-500Thermostat Digital872.49.3
BRG-340Bearing 1" Sleeve1194.724.8
MTR-725Motor 1/4HP 1075RPM665.231.2
VLV-190Solenoid Valve 1/2"983.619.5
SEN-410Temp Sensor NTC762.912.4
FUS-025Fuse 25A Cartridge1082.210.8
BLT-150Blower Belt B-Section553.316.9
IGN-870Igniter HSI 120V444.121.3
TRM-620Transformer 40VA653.817.2
GAS-310Gas Valve Nat 3.5"WC335.629.7
PRE-540Pressure Switch543.413.5

Forecast MAPE vs. Stockout Rate

Inventory Carrying Cost by Van (Top 12)

Supplier Lead-Time Adherence

On-Time Deliveries 91.4%
Mean Lead-Time Variance +1.8 days
Late Orders (30d) 23
Critical SKUs Delayed 5