Financial Governance & Cost Performance Intelligence

Vantara Energy Services PMO | Active Portfolio: $62.4M across 16 projects

As of Period 12 (Dec 2024)
Target: Portfolio CPI ≥0.90 | EAC Accuracy ≤12%
Portfolio CPI
0.91
↑ 5.8%
EAC Accuracy
9.4%
↓ 3.2pp
Contingency Drawdown
87%
vs 92% risk mat.
Vendor Variance
+$4.2M
↑ $1.1M
Avg Cost of Delay
$1.8M/w
Weighted avg
Uncommitted Budget
$8.3M
13.3% of total
Portfolio Cumulative Spend: Planned vs. Actual
CPI Trend by Program (12-Period Rolling)
EAC Waterfall: Original Budget → Current EAC
Contingency Drawdown vs. Risk Materialization (Cumulative $M)
Vendor Cost Variance by Supplier ($M)
TechBuild Partners +$3.0M (+24%)
GridSys Solutions +$1.2M (+11%)
Apex Engineering -$0.3M (-3%)
Delta Contractors +$0.2M (+2%)
EnergyCo Services -$0.7M (-8%)
Base contract value total: $38.2M | Current: $42.4M
Budget Release Velocity vs. Milestone Achievement (%)
Project Financial Health Register (Top 8 by Budget)
Project Name Program CPI EAC Acc % FGS Budget ($M) Status Alert
Grid Modernization Phase 2 Gamma 0.84 18.2% 62 $14.8 Critical 14 unapproved COs
Offshore Wind Integration Alpha 0.96 4.1% 94 $12.2 On Track
Smart Metering Rollout Beta 0.91 7.8% 88 $9.6 On Track
Battery Storage Expansion Gamma 0.88 12.4% 76 $8.1 Watch Contingency 95% used
Transmission Uprate Alpha 0.93 6.3% 89 $6.4 On Track
SCADA Upgrade Beta 0.87 14.7% 71 $4.9 Watch Vendor variance +18%
Substation Hardening Delta 0.98 2.1% 97 $3.7 On Track
Renewable Interconnect Gamma 0.82 21.3% 58 $2.7 Critical EAC revised 3x
Uncommitted Budget at Risk vs. Portfolio CPI (12-Period Trend)
Action Required: Program Gamma Financial Review
TechBuild Partners change order governance breakdown detected — 14 approved COs with no documented cost impact assessments. Immediate audit scheduled for Jan 6, 2025. Portfolio NPV exposure: estimated $2.8M if trend continues.